Designs

Correct Data Center Design requires:

  • Hardware count
  • IT Load determination
  • Future overhead considered
  • Rack count
  • Heat dissipation and therefore cooling requirements
  • Air Flow analysis CFD based on rack layout to prove the design
  • Monitoring requirements. Temperature, humidity, power consumption, cooling system metrics, power usage effectiveness (PUE) etc.
  • Fire Suppression type and capacity
  • Backup Power requirements, IT plus Cooling Load
  • Backup Power sustainability

Some examples of Data Center designs in which we have been involved:


24 Rack Backup Site


Floor Plan

Building construction

Dropped slab sloped for floor drains and raised floor

Raised Floor installation

Drop slab with raised floor meets building floor

Geothermal Heat Pump delivery, Electrical Room wall construction

CFD Model with client design heat pumps only - proof positive that Heat Pumps alone will not cool the room

CFD Model - our design for total capacity




40 Rack Primary Site


Floor Plan

CFD Model

Interior wall installation

Drywall completion - slab to slab

Glycol/water loop sanity check

The cooling loops take shape

Fluid Cooler delivery

Fluid Cooler crane lift

Fluid Cooler Fan Farm complete

Cooling loops and floor completion

Cooling loops under the floor

Cooling Loop building exit, insulation and control valves

CRAC unit crane lift

Running on Energy Saver cooling - no compressors run below 10 degrees C.




36 Rack Primary Data Centre


Floor Plan

Computer Room

UPS Room

Electrical Install

GrateAire perf tiles for combination Blade/Rackmount server racks




60 Rack Backup Data Centre


Floor Plan

VAV air to personnel spaces going in

Pipe Delivery

Welding the glycol underfloor loops

Glycol loops to the roof

Loops from below complete and insulated

Completed rooftop loops

Glycol pumps

Fluid Cooler array

Phase rotation check and wire

Raised floor complete. Stands ready for CRAC units.

CRAC units in and ready for commissioning

Commissioning and startup

Personnel space to Data Centre connection array

Starline Busway going in

Busway and rack chimneys complete

Mitsubishi Parallel UPS system

Data Centre panels

Racks in. Cold aisle.

UPS systems commissioning and load bank test




400 Rack Primary Data Centre - Initial Construction/Operations collaboration, Ongoing Facilities Management


The Base Building

Completed Hall Corridor

Rack Suite Power Panels A+B

EPCOR installing new upgraded transformer

Input transformer being put in place

EPCOR tie-in across the street

UPS Room raised flooring in, other material storage

Annual fire pump test

Connecting test trailer to the fire standpipe connections

Switchgear completion in preparation for commissioning

Rack Hall, ready for clients

Munters air handler being crane lifted into place

A training slide I did for onsite staff

Freeze protection system completion. This is the air handler release valve and standpipe.

Switchgear complete and being utilized

Data Centre Design Inc. battery monitoring system rough-in. Design, build and configure.

Data Centre Design Inc.evap water cooling system monitors added



Contact us at jamie@datacentredesign.ca

Vendors we work with if you have no preference:

© 2024 | Data Centre Design Inc. | All Rights Reserved